The contractor is utilizing the new concrete floor slab for a platform on which to form and pour the concrete tilt up panels for the exterior walls of the building. Approximately half of the wall panels needed have now been poured and when all of the panels are poured and cured, the panels will be lifted to a vertical position to form the walls. The erection of structural steel framing system that supports the roof area will follow.
 