We have been blessed with favorable weather this week and the contractor will have the concrete wall panels lifted and braced in a vertical position to form the main corridor walls and all of the exterior walls except for the east wall of the auditorium and west wall of the education wing. These remaining wall panels are scheduled to be formed and poured next week and lifted into place the following week. The erection of structural steel framing system that supports the roof area will start next week in the education wing.
Site work is also continuing with installation of the domestic water main and with the grading of the entrance roadway from Wyatt and the south parking area.